What is the most you could pay for this site?
Residual land value answers the only question that matters before you make an offer: what can the land be worth to this scheme, at the margin you require. Everything the site sells for, less everything it costs to build and sell, less the profit you will not go below, is what is left for the dirt.
This calculator does not evaluate a formula. It scales the land price and re-runs the entire appraisal at each step until the margin on cost lands on your target — the same solver the product runs on a full scenario.
Your scheme
Demonstration figures — edit any field.
Total sales revenue for the scheme.
Build cost, excluding GST.
Professional fees, contingency, marketing and agents combined, excluding GST.
Profit as a percentage of total development cost.
Maximum land bid
- Maximum land bid
- $791,015.63
- Revenue (ex GST)
- $10,909,090.91
- Total development cost
- $9,091,015.63
- Profit
- $1,818,075.28
- Margin on cost
- 20.0%
Solver assumption: acquisition costs held at entered values. Acquisition costs such as transfer duty are not re-derived at the solved bid. The appraisal runs on a 24-month program with no debt or equity entered, so funding costs are zero.
How do you calculate residual land value?
The shape of it is simple. Gross realisation — what the finished product sells for — less the GST inside that revenue, less construction, professional fees, contingency, marketing and agents, less the profit you require, leaves the residual. Every appraisal textbook prints some version of that line.
The trouble is that the line is circular. Interest depends on how much you borrow, which depends on what you pay for the land. Facility sizing depends on total cost, which includes the land. Solve the line once with funding costs frozen at your guess and you get an answer that is right about arithmetic and wrong about money.
Why solving beats a closed-form answer
The engine behind this page bisects on a single land factor: it scales every land lot’s purchase price by one common multiplier, recomputes the whole appraisal — cost base, drawdown, interest, margin — and moves the bracket until the margin on cost sits on your target. Because each probe is a full appraisal, funding costs move with the bid instead of being held at the price you started from.
That is also why a solved bid can legitimately differ from the residual land value line in a summary table. Both are worth looking at; only one of them re-derives interest.
What the answer holds constant
The solver states its own limitation, and the calculator prints it rather than hiding it: acquisition costs held at entered values. Transfer duty is the one that bites — duty on a site scales with the price you pay for it, so a bid solved with duty held at its entered figure is slightly optimistic. Price the duty on the development site duty calculator and add it to your other costs to close most of that gap.
Three other simplifications are worth naming. The appraisal runs a 24-month program, because a public screen does not ask for a program. No debt or equity is entered, so funding costs are zero and the answer is an ungeared ceiling. And the whole gross realisation is treated as one settlement at the end, rather than a settlement profile across the last months of the scheme.
Why the GST treatment changes the answer
Profit is measured on revenue net of GST. If your gross realisation is stated GST inclusive, one eleventh of it is not yours, and the residual falls accordingly. If the sales are input taxed or otherwise GST exempt, the whole figure is revenue. On a $12m scheme the difference between those two readings is over $1m of revenue — and most of that lands on the land price.
If the site qualifies for the margin scheme, the GST wedge is smaller again. The margin scheme calculator shows by how much.
Worked example
Demonstration figures
A scheme with a $12,000,000 gross realisation stated GST inclusive, $6,500,000 of construction and $1,800,000 of other development costs, at a 20% target margin on cost.
| Gross realisation (GST inclusive) | $12,000,000 |
|---|---|
| Revenue net of GST | $10,909,091 |
| Construction | $6,500,000 |
| Other development costs | $1,800,000 |
| Maximum land bid | $791,015.63 |
| Total development cost at that bid | $9,091,016 |
| Profit at that bid | $1,818,075 |
| Margin on cost achieved | 20.0% |
Change one input and watch which way the bid moves. Add $500,000 of construction and the land bid falls by more than $500,000, because the required profit is a percentage of a cost base that just grew. That asymmetry is the whole reason a residual is solved rather than subtracted.
Frequently asked questions
How do you calculate residual land value?
You start from what the finished scheme sells for, take out everything it costs to build and sell, take out the profit you require, and whatever is left is what the land can be worth to you. The textbook form is gross realisation less development costs less required profit; the difficulty is that several of those costs — interest above all — depend on the land price you are solving for.
Why does this calculator solve rather than use a formula?
Because a closed-form residual value holds funding costs at the land price you entered, which is the price you are trying to find. This calculator scales the land price and re-runs the whole appraisal at every step, bisecting until the margin on cost lands on your target, so interest and facility sizing move with the bid instead of being frozen at a guess.
What does the calculator hold constant?
The solver's stated limitation is that acquisition costs held at entered values — acquisition costs such as transfer duty and legal fees are not re-derived at the solved bid. It also runs a 24-month program with no debt or equity structure entered, so funding costs are zero. A real appraisal enters both, and the answer moves.
Is residual land value the same as market value?
No. It is the most this scheme, at this target margin, could pay — a bid ceiling, not a valuation. Another buyer with a different scheme, a lower margin requirement or cheaper money will have a different residual value for the same site, which is why sites sell above what a given developer can justify.
What margin should I target?
That is a commercial and financing question, not a formula. Margin on cost is profit as a percentage of total development cost, so a target sits on the risk of the scheme and on what a lender wants to see before it funds. The calculator takes whatever figure you enter and does not imply one is correct.
Why does it say no bid meets the target?
Because even free land would not reach the margin you asked for: the costs are too close to the revenue. That is a real answer about the scheme, not an error — it means the deal needs a different cost base, a different product mix or a different target before land price is the question.
Solve the bid on the real scheme
The free Feasibility tier runs this solver on a full appraisal — your actual unit mix, cost lines, program and funding structure — instead of four summary numbers.
Start freeFeasibility is free — 3 feasibility projects at a time, no card.
Sources
- UpScale.build — residual land value solver (src/lib/feasibility/rlv.ts) — accessed 17 September 2026. The method and its stated limitation are the engine's own; this page imports it rather than restating it.
- ATO — GST and property — accessed 17 September 2026. Why the GST treatment of the gross realisation changes the residual value.
The other calculators
- GST margin scheme calculator — GST under the margin scheme against 1/11th of the price, plus the eligibility and withholding questions that decide which one you pay.
- Development site stamp duty calculator — Transfer duty and the foreign purchaser surcharge on a development site in NSW, VIC, QLD or WA, on the published revenue-office scales.
- NSW land tax calculator — What a development site costs you to hold each year: NSW land tax on the published thresholds, plus the foreign owner surcharge.
- Quick feasibility calculator — Screen a site from ten numbers: margin on cost, profit, peak funding and the month funding peaks. Everything is computed in your browser.
General information, not tax, legal or financial advice. Confirm with your accountant or solicitor. A residual land value is a bid ceiling for one scheme at one target margin. It is not a valuation and it is not an offer recommendation.