Scope of works template for a residential development
A scope of works template has one column that most versions of it skip, and it is the one that ends the most arguments: exclusions. What is included in a trade’s price gets written down as a matter of course. What is deliberately left out — the rock below a stated level, the item another section supplies, the condition a section has to be handed over in — is the boundary a scope actually needs to draw, and it is the field a scope with no exclusions is silently missing. This page is not a document to sign. It is a structure: one row per section of the works, one trade or work package at a time, repeated until the contract is fully described.
What is a scope of works for?
It is written for whoever has to draft or assess the document that turns a design into a priced scope: a client-side project manager assembling a head contract package, a head contractor writing scope for its own subcontract packages, or a superintendent checking that what was tendered is what gets built. A drawing set and a specification show a tenderer what the finished work looks like. The scope of works states what they are actually pricing — what is included, what is excluded, what is carried as an allowance because it can’t yet be priced, and where their section hands over to the next. Background on what the document itself has to do is in scope of works.
Every section is numbered, and the numbering has to stay stable, because the tender, the schedule of rates, every progress claim and the final account all point back to it. That is also why this is the document a tender is actually priced against: how it sits alongside the drawings and the specification at that stage is covered in the tender process.
| Field | What goes in it | Bayside Townhouses (demo) |
|---|---|---|
| Project | The project the contract belongs to. | Bayside Townhouses (demo) |
| Section no. | The section's number in the scope. Number the sections and keep the numbering stable, because the tender, the schedule of rates and every claim will refer to it. | 3.2 |
| Section | The trade or work package this section covers, named the way the market names it. | Bulk earthworks and basement excavation |
| Inclusions | What is in the price. Write it as work to be performed, not as an object supplied, so the labour to install it is not later argued to be extra. | Bulk excavation to design levels, shoring design and installation, dewatering, cart-away and disposal of spoil to a licensed facility, and set-out survey. |
| Exclusions | What is deliberately not in the price. An exclusion that is not written down is a variation waiting to happen, and this is the field that most often decides one. | Removal or treatment of contaminated material; rock excavation below RL 11.8; remediation of pre-existing site contamination. |
| Provisional sums | Work that is in scope but cannot yet be priced, carried at an allowance and adjusted on the measured or actual cost. State the allowance and what triggers the adjustment. | $40,000.00 - rock excavation below RL 11.8 if encountered, adjusted on measured quantity at the scheduled rate. |
| Prime cost items | Items that are in scope but not yet selected, carried at a supply allowance with the installation already priced. Say what the allowance covers and what it does not. | Nil for this section. |
| Interfaces | Where this section hands over to another, in both directions, and what condition the work has to be in at the handover. Most defects arguments live in this field. | Hands over to the structure package at completion of the blinding layer, surveyed and signed off. Shoring design to be coordinated with the structural engineer before excavation starts. |
| Standards and codes | The standards and codes the work has to meet, including the National Construction Code and any standard the specification names. Reference them; do not restate them. | National Construction Code, and the earthworks, geotechnical and shoring standards named in the contract specification. |
| Deliverables | The documents that have to be handed over for the section to be complete: certificates, test results, warranties, as-built drawings, dockets. | Shoring design certification, dilapidation survey of adjoining properties, spoil disposal dockets, and a set-out survey report. |
| Responsible party | Who performs the work, and who supplies anything the performer does not. Split responsibility here rather than in a meeting later. | Head contractor |
| Notes | Assumptions, access constraints, staging, and anything a tenderer would have to ask about if it were not written down. | The exclusion and the provisional sum here cover the same physical event the variation register carries as VO-12, written the other way round. Excluded from the scope and carried at a provisional sum, rock is priced before it is hit; left out of the scope entirely, it arrives afterwards as a latent condition to be argued. |
How to fill this in
- Write one section per trade or work package and keep the numbering stable. The tender, the schedule of rates, every progress claim and the final account will all point back to these numbers.
- Exclusions do more work than inclusions. A scope that lists only what is included leaves every boundary to be argued at the first claim; the demonstration row excludes rock below a stated level and then carries a provisional sum for it, which is the pair that makes the risk priced rather than disputed.
- A provisional sum is work in scope that cannot yet be priced. A prime cost item is an item in scope that has not yet been selected. They adjust differently, so keep them in separate fields.
- Interfaces are where the defects come from. State what condition the work must be in at handover and who inspects it, in both directions.
- Reference standards; do not reproduce them. Standards Australia publishes the Australian Standards a specification calls up, and the National Construction Code is published by the Australian Building Codes Board.
- General information, not legal advice. Read your own contract and confirm your position with your solicitor.
How do you fill in each section?
The section header — project, section number, section name — is what everything else in the row hangs off. Keep the numbering stable once the tender goes out; a schedule of rates, a progress claim and a variation register all refer back to a section number, and a section renumbered between tender and contract is a section nobody’s paperwork agrees on any more.
Inclusions and exclusions are the pair that decides the boundary. Write inclusions as work to be performed rather than an object supplied, so the labour to install it can’t later be argued as extra. Then write the exclusion for anything a reasonable tenderer might assume is included but isn’t — the demonstration row excludes rock excavation below RL 11.8, because without that line a tenderer could reasonably assume all excavation, at any depth, sits inside the bulk earthworks price.
Provisional sums and prime cost items are answered by different questions, so keep them in separate fields. A provisional sum is work already in the scope that can’t yet be priced — the demonstration row (section 3.2) carries a $40,000.00 allowance for rock excavation below RL 11.8, adjusted on the measured quantity if it is actually encountered. A prime cost item is work in scope where the item itself hasn’t been selected yet, carried at a supply allowance with the installation already priced. Neither is a way of avoiding a decision; both are a way of pricing scope before the decision is made.
Interfaces, standards, deliverables and responsible party close the section out. Interfaces are where most defects arguments start, so state the condition the work has to be in at handover, in both directions, and who inspects it. Standards should be referenced — the National Construction Code and whatever Australian Standards the specification calls up — never restated, because the specification’s own wording is what actually applies. Deliverables are the documents a section isn’t complete without: certificates, test results, warranties, as-built drawings. Responsible party is who performs the work and who supplies anything the performer doesn’t, and it belongs in the scope rather than in a meeting after the fact.
What goes wrong with a scope of works?
Inclusions with no exclusions beside them. A scope that lists only what is included leaves every boundary to be argued at the first claim. Write the exclusion next to the inclusion it borders, not on a separate page nobody reads at tender.
A provisional sum with no trigger stated. An allowance sitting in a scope with no stated trigger for when it applies is an allowance nobody can adjust with a straight face at claim time. State what has to happen — a level, a measured quantity, a defined event — before the sum moves.
An interface with a handover but no inspection. Say who inspects the work at the boundary and what condition it has to be in. A handover with no inspection named is where a defect quietly becomes the next trade’s problem instead of the last one’s.
Expecting to edit the scope inside the template. The download is a structure to write a scope against, not the scope itself. The prose that actually describes the work — the wording a tenderer prices — still gets written in your own document; this template is the list of fields that document has to answer, not a replacement for writing it.
Download the template
Free, no email required. Both files carry the same demonstration row you can see above — delete it and type over the structure.
The PDF is the template as a printable form, with a blank column to write in. This one has no CSV: a scope of works is prose in a structure, and a spreadsheet cell is the wrong shape for it.
Frequently asked questions
What is the difference between a provisional sum and a prime cost item?
A provisional sum is work that is already in the scope but cannot yet be priced with any accuracy, so it is carried as an allowance and adjusted once the work is measured or its actual cost is known. A prime cost item is different: the item itself has not been selected yet, but the installation is already priced, and the allowance covers only the supply. In the demonstration row on this page, the rock excavation below RL 11.8 is a provisional sum of $40,000.00, because nobody yet knows whether it will be needed. Keep the two in separate fields, because they are answered by different questions and reviewed differently at claim time.
What belongs in the exclusions of a scope of works?
Exclusions are what is deliberately left out of the price, and they do more work in a scope than the inclusions do. A scope that only lists what is included leaves every boundary to be argued at the first claim. In the demonstration row, the exclusion is rock excavation below RL 11.8, paired with a provisional sum for the same event, so the risk is priced before it happens rather than argued about afterwards. If a boundary a reasonable tenderer might assume is covered isn't written into the exclusions, it isn't a saving — it's a variation waiting to happen.
Does a scope of works template come as a Word file or a spreadsheet?
This one doesn't. The download here is a PDF: a printable structure of the sections, inclusions, exclusions, provisional sums, prime cost items, interfaces, standards and deliverables a scope needs, with a blank column to write into. It is not an editable Word file you can type straight into, and there is no spreadsheet version — a scope is prose written against a structure, not a row of figures. What this template gives you is the list of fields that prose has to answer. The scope itself, the actual wording describing the work, is still written in your own document.
Why is one row of this template one section, not one project?
Because a scope of works isn't a single figure the way a claim is — it is a document made of sections, one for each trade or work package, and every section carries its own inclusions, exclusions, provisional sums and interfaces. One row of this template is one of those sections, repeated for every trade in the contract, not one row per project. A residential development can run to dozens of sections before the scope is complete, and numbering them and keeping that numbering stable is what lets the tender, the schedule of rates and every later claim point back to the same reference.
How does a scope of works fit into the tender process?
The scope of works is one of the documents a tenderer prices against, alongside the drawings and the specification. Ambiguity in the scope becomes a qualification in a tender, or a variation once the contract is signed, so a scope written section by section, with inclusions and exclusions stated rather than assumed, is what lets tenders be compared on the same basis. A tenderer working from a scope with no exclusions will price it however suits their number, and every gap between tenderers then becomes a question you have to chase down instead of a figure you can compare directly.
Keep this register live in UpScale
A scope is the reference point every later progress claim is measured against and every variation is written as a change to. UpScale.build keeps the scope, the variations and the claims against the same contract, so the section a claim references is the section you actually wrote.
Start freeFeasibility is free — 3 feasibility projects at a time, no card. Or read construction project management software first.
Sources
- National Construction Code (Australian Building Codes Board) — accessed 2026-09-17. The code a scope of works references when it says work is to be built to the NCC. Referenced, not reproduced.
- Standards Australia, publisher of AS 4000-1997 and AS 2124-1992 — accessed 2026-09-17. The Australian standard form head contracts a scope of works is annexed to, and the publisher of the Australian Standards a specification calls up. Their text is copyright and is not reproduced here.
The other templates
- Progress claim template — A payment claim schedule for a NSW head contract, with the payment-schedule fields the principal has to answer.
- Construction variation template — A variation request and register: origin, cost breakdown, time impact, the contract clause it is directed under, and the approval chain.
- Construction RFI template — An RFI form and register: question, drawing and specification reference, who has to answer, by when, and whether the answer costs money or time.
- Construction meeting minutes template — Site and PCG meeting minutes: attendees, apologies, safety, programme, RFIs, variations, claims, and actions with an owner and a due date.
General information, not legal advice. These templates are a starting structure, not a contract document: read your own contract, and confirm your position with your solicitor before you rely on any of it. This page names the National Construction Code, AS 4000-1997 and AS 2124-1992 to describe the kind of provision a scope of works references. It does not state any clause number or reproduce any clause or code text, and it is not a substitute for reading the code or the standard itself.