Construction RFI template and register

A construction RFI template has two halves that most versions of it only have one of. The first is the question: one thing, stated precisely enough to be answered with a yes, a no or a dimension, tied to the drawing revision and specification clause it’s actually about. The second is the answer: who gave it, on what date, and whether it changes the cost or the programme. A register that only tracks the first half is a list of things asked, not a record of what the project is actually being built to.

What is an RFI in construction?

RFI stands for request for information. It’s the mechanism a contractor uses to ask the design team or the client-side project manager a specific question about the contract documents — a drawing, a specification section, a detail that is missing or that two documents answer differently — and to get that answer in writing before the work in question is built. An RFI is a question, not an instruction and not a change: the standard format has one question, a drawing and specification reference, a date the answer is needed by and why, the written response, who gave it, and whether the answer carries a cost or time impact. The demonstration row on this page, RFI-041 (Bayside Townhouses (demo)), shows that format working end to end: a genuine clash between a drawing and a specification, answered in writing by the person with authority to answer it, closed once the answer was reflected in a reissued drawing.

This template is written for whoever runs the register on a live job: the site manager who raises the question and needs a paper trail if it turns into a variation, or the project manager who has to know at a glance which questions are still open and which are sitting past the date they were needed by. It works the same way on any Australian head contract, because raising a written question about the documents and getting a written answer is a contract-administration practice, not a mechanism a particular standard form or code sets out. Background on when an answered RFI stops being an RFI and starts being a variation is in RFI in construction, and on what happens next in variations in construction.

RFI form and register — one demonstration row, Bayside Townhouses (demo). The figures are for the walkthrough, not a record of a real project.
FieldWhat goes in itBayside Townhouses (demo)
ProjectThe project the RFI belongs to.Bayside Townhouses (demo)
RFI no.A number that is never reused. Drawings, minutes and variations all point back to it.RFI-041
Date raisedThe date the RFI was issued, not the date the problem was noticed. If those differ by weeks, that is its own problem.2026-08-10
Raised byThe person and the organisation asking. A question from the site is answered differently to one from an estimator.Site manager, head contractor
DisciplineArchitectural, structural, civil, hydraulic, mechanical, electrical, fire or landscape. Discipline is what routes the RFI to the consultant who can answer it.Structural
QuestionOne question, stated so it can be answered yes, no, or with a dimension. An RFI containing three questions gets one answer and stays open.Drawing S-204 rev C shows the basement slab thickening at grid D/4 as 450 mm. The structural specification for the same element calls up 500 mm. Which governs?
Drawing / specification referenceThe drawing number and revision, and the specification clause. A reference without a revision number is not a reference.S-204 rev C; structural specification section 3.4
Response required byThe date the answer is needed to avoid affecting the programme, with the reason it is that date.2026-08-14 - slab thickening is on the critical path for the 17 August pour
ResponseThe answer, in writing, from the party with authority to give it. Verbal answers on site are not responses.500 mm governs. S-204 to be reissued as rev D with the thickening corrected. No change to reinforcement.
Responded byWho answered. An answer from someone without design authority is an opinion, not a direction.Structural engineer
Date respondedThe date the written response was issued. The gap between this and the date required is the number that matters at the end of the job.2026-08-13
Cost impactWhether the answer changes cost, and the variation number if it does. Yes with no variation number is an open exposure.No
Time impactWhether the answer changes the programme, and the extension-of-time number if it does.No
StatusOpen, answered, or closed. Answered and closed are not the same: closed means the site has what it needs.Closed
Date closedThe date the RFI was closed out and the answer reflected in issued documents.2026-08-13

How to fill this in

  • An RFI is a question about the contract documents, not a change to them. The moment the answer changes scope, cost or time, it stops being an RFI and starts being a variation - raise one, and write its number in the cost impact field.
  • One question per RFI. The register in the demonstration row closes in three days because the question can be answered with a dimension.
  • The response required by date needs a reason beside it. A date with no reason gets treated as a preference; a date tied to a pour, a delivery or a critical-path activity gets treated as a deadline.
  • Close the RFI only when the answer is in an issued document. An answer that lives only in the register is an answer the next trade will not find.
  • General information, not legal advice. Read your own contract and confirm your position with your solicitor.

How do you fill in each field?

The identification block — project, RFI number, date raised, raised by, discipline — is what makes the register searchable in six months. RFI-041 is never reused, even if the RFI is later cancelled; discipline is what routes the question to structural, architectural or whichever consultant can actually answer it.

The question and reference block should stand alone: one question, answerable with a yes, a no or a dimension, next to the drawing revision and specification clause it’s about. In the demonstration row the question is exactly that shape — drawing S-204 rev C shows a basement slab thickening of 450 mm at grid D/4, the structural specification section 3.4 calls up 500 mm, and the question is simply which one governs.

Response required by needs a reason attached, not just a date. In the demonstration row the reason is that the slab thickening sits on the critical path for the 17 August pour, which is what turns 2026-08-14 from a preference into a deadline the site actually has to hit.

The response itself has to come from someone with design authority over that discipline, in writing — a verbal answer on site is not a response, however senior the person giving it. In the demonstration row the structural engineer’s answer, that 500 mm governs and S-204 is to be reissued as rev D, is dated 2026-08-13, a day inside the 2026-08-14 deadline.

The cost and time flags are where an RFI meets a variation. If the answer changes what was priced or programmed, the flag has to carry a variation or extension-of-time number, not just a yes — track that number separately in the variation register. A head contract like AS 4000-1997 or AS 2124-1992 will have its own notice provisions and its own direction and variation clauses governing what happens once an answer changes scope, cost or time — read those clauses in your own contract rather than in this template. The demonstration row closes with no cost and no time impact, which is why it can go straight to closed rather than spinning off a variation number.

What goes wrong with RFIs?

More than one question in an RFI. A three-part question gets a two-part answer and stays open on the part nobody addressed — better to raise three RFIs than one that never fully closes.

A reference with no revision number. “See S-204” is not a reference once that drawing has been reissued twice; “S-204 rev C” is, because it tells the next person reading the register exactly which version the question and the answer were about.

Accepting a verbal answer on site and never following it up in writing. It might be the right answer, but the site has now built to an instruction nobody signed, and the paper trail a variation claim needs later does not exist.

Closing the RFI before the answer is reflected in an issued document. Marking the row closed the day the response arrives, before the drawing is reissued or the specification amended, means the next trade to open the drawing register is still working off the superseded page.

Download the template

Free, no email required. Both files carry the same demonstration row you can see above — delete it and type over the structure.

The CSV is the register: one header row of fields and the demonstration record. The PDF is the same template as a printable form, with a blank column to write in.

Frequently asked questions

What does RFI stand for and what's the standard format?

RFI stands for request for information. There's no single mandated form in Australian construction, but the elements that make one useful are consistent: a number that's never reused, the date it was raised, who's asking, which discipline it belongs to, one question stated so it can be answered with a yes, a no or a dimension, the drawing and specification reference it relates to, the date an answer is needed by and why, the written response and who gave it, and whether the answer changes cost or programme. The sample row on this page, RFI-041, shows that format filled in end to end, from a genuine drawing-versus-specification clash through to a written answer and a closed date.

When does an RFI turn into a variation?

The moment the answer changes what was priced or programmed, not before. Asking which of two conflicting dimensions governs is an RFI; being told to change the design, upgrade a finish or move a service is a variation, even if it arrives as an answer to an RFI. Head contracts such as AS 4000-1997 and AS 2124-1992 each carry their own notice provisions and their own clauses covering directions and variations, so what has to happen procedurally once an answer changes scope depends on your own contract. Treat the cost and time flags on this template as the trigger: the moment either is 'yes', raise a variation or an extension-of-time claim with its own number, and record that number in the flag rather than leaving it as a description.

How specific does an RFI question need to be?

Specific enough to be answered with a yes, a no or a dimension. The demonstration row is a good model: drawing S-204 rev C shows a slab thickening of 450 mm, the structural specification section 3.4 calls up 500 mm, and the question is simply which one governs. A vague question invites a vague answer, and a vague answer is the thing that gets argued over later. If a genuine question has more than one part, raise it as more than one RFI. One question per RFI keeps each row able to close on its own, rather than sitting open because only part of it was ever answered.

Who should be able to answer an RFI?

Whoever holds design authority over the discipline the question belongs to — the structural engineer for a structural question, the architect for a detail, the hydraulic consultant for a drainage point — not whoever happens to be on site that day. A verbal answer from an authorised person might be correct, but it leaves no record, so this template treats a response as the written answer from the person named in the responded-by field, on the date it was issued. In the demonstration row that's the structural engineer, answering in writing a day before the date the answer was needed by.

When should an RFI be closed?

Once the answer is reflected in an issued document, not on the day the written response arrives. In the demonstration row the response comes back on 2026-08-13 stating that drawing S-204 will be reissued as rev D with the corrected thickening; the row can be marked closed the same day only because that reissue is confirmed, not assumed. Marking an RFI closed before the drawing or specification is actually updated leaves the next person to open the register with a status that says the question is settled, while the document they're building from still shows the old information.

Can I use this RFI template on any project?

Yes. Nothing about an RFI's structure — a numbered question tied to a drawing and specification reference, a date it's needed by, a written answer, and cost and time flags — depends on which state or territory the project is in, or which standard head contract it sits under. What differs between contracts is what a direction or a variation clause requires once an answer changes scope, cost or time, and that's a matter for your own contract rather than for this template. Keep the register's structure, and confirm the procedural steps that follow a cost or time flag against the contract you're actually working under.

Keep this register live in UpScale

An RFI register that stops updating once the drawing is reissued is a register nobody trusts by the second month of a job. UpScale.build keeps RFIs, drawings and variations against one contract, so a cost or time flag on an RFI is one click from the variation or extension of time it created.

Start free

Feasibility is free — 3 feasibility projects at a time, no card. Or read construction project management software first.

Sources

The other templates

  • Progress claim template — A payment claim schedule for a NSW head contract, with the payment-schedule fields the principal has to answer.
  • Construction variation template — A variation request and register: origin, cost breakdown, time impact, the contract clause it is directed under, and the approval chain.
  • Scope of works template — A scope of works structure for a residential development head contract: inclusions, exclusions, provisional sums, PC items, interfaces, standards and deliverables.
  • Construction meeting minutes template — Site and PCG meeting minutes: attendees, apologies, safety, programme, RFIs, variations, claims, and actions with an owner and a due date.

General information, not legal advice. These templates are a starting structure, not a contract document: read your own contract, and confirm your position with your solicitor before you rely on any of it. The Australian Standards named on this page decide when an answered RFI has become a variation through their own notice and direction provisions; their clause text is copyright and is not reproduced here. This page does not state a legislated or standard-form response time for an RFI, because none exists — the response-required-by date is a programme decision, not a statutory one.