Extension of Time (EOT)
An extension of time is a formal claim by a contractor for additional time to complete the works due to qualifying causes of delay beyond their control.
An extension of time — or EOT — is the contractor's mechanism for getting more time when things outside their control delay the project. Rain that exceeds historical averages, design changes directed by the principal, late access to the site, even global pandemics — these can all be qualifying causes for an EOT.
Why does this matter to a developer? Because the contract completion date isn't just a target — it's a legally binding obligation with financial consequences. If the contractor finishes late without an approved EOT, they owe you liquidated damages (LDs). But if they have a valid EOT that you failed to assess properly, those LDs are unenforceable.
The EOT process is time-sensitive. Most contracts require the contractor to give notice within a set number of days of the delay occurring. The superintendent then has to assess the claim and either approve days, reject the claim, or approve a different number of days. Every step needs to be documented.
For developers, EOTs also have cash flow implications. A longer construction period means extended holding costs — interest on your development finance, extended prelims, and potentially delayed settlement income. Even a two-week extension can cost tens of thousands on a leveraged project.
How UpScale Handles This
UpScale tracks every EOT claim with the days claimed, days approved, cause of delay, and impact on the completion date. You can see at a glance how your program is tracking against the original contract date and make informed decisions about how delays affect your project timeline and budget.
Related Terms
Variations (Construction)
A variation is a change to the original scope, cost, or timeline of a construction contract, formally documented and requiring approval before work proceeds.
Practical Completion
Practical completion is the contractual milestone when a building is sufficiently complete for its intended purpose, triggering key obligations like defects liability and final payment.
Site Diary
A site diary is a daily record of activities, conditions, and events on a construction site, serving as a contemporaneous log for project management and dispute resolution.